The ground over the unfinished tunnel of the Haryana Orbital Rail Corridor (HORC) sank for a sixth time early on Sunday morning, November 22, in Sahsola village in Nuh district's Taoru subdivision, cracking several houses and forcing families to leave their homes.

Villagers told The Tribune that a loud bang woke them early in the morning and that they found deep pits in the fields next to their homes. One house, roughly 200 feet of village road and a stretch of land over 400 feet long went down, and the sinking ground crossed the barricades put up by the district administration.

Source: The Tribune

Many families have locked their houses and left — some for rented rooms and some for makeshift huts, taking their cattle with them. No one was hurt in the latest collapse.

Six collapses in seven weeks

The trouble began in early October in Patuka, part of the same panchayat, where residents wrote to the Nuh deputy commissioner on October 5 asking for the work to be stopped. A bigger collapse on October 10 damaged a government school and a house, dropped more than 500 metres of land and exposed a GAIL gas pipeline.

Further collapses came on October 30 and November 4, when a government road gave way. Crews filled it with soil and it sank again on November 18. About 10 to 12 acres of farmland in Patuka have been ruined, crops included. The pipeline was not hit this time.

Work stopped, land acquisition under way

A senior official of the Haryana Rail Corporation told The Tribune that the repeated collapses had upset the ground at the site. Work has stopped and the tunnel's starting point has been backfilled. Houses nearby were inspected and marked, and land acquisition has started.

Digging will resume only after the land is acquired, on a new design shaped by the expert committee's report, the official said. That committee has not published its findings. Villagers allege negligence and say no real safety measures were taken.

The corridor is a 126 km double-line railway from Palwal to Sonipat through Sohna, Manesar and Kharkhoda, with a 4.7 km twin tunnel through the Aravalli hills. Officials raised its estimated cost this year from Rs 5,618 crore to Rs 11,709 crore, according to The Tribune.

What happens next

The expert committee's findings and the new tunnel design will decide when — and how — digging resumes. Until the land is acquired, the tunnel work stays stopped.