Georgia voters have handed Democrats control of the state's powerful Public Service Commission for the first time in 30 years, winning both seats on the November 3 midterm ballot and with them the majority that will decide what nearly three million Georgia Power customers pay for electricity — and who pays for the data-centre boom now driving the state's power demand. Democrat Peter Hubbard defended his District 3 seat against former commissioner Fitz Johnson, the Republican he had unseated a year earlier, and Democrat Shelia Edwards defeated Republican Josh Tolbert for the open District 5 seat recently vacated by Tricia Pridemore. When the new terms begin in January, Hubbard and Edwards will join District 2 Commissioner Alicia Johnson to give Democrats three of the five seats on the commission.

Source: The Current GA / Georgia Public Broadcasting, Nov. 4, 2026

3–2Democratic majority on the five-member Georgia Public Service Commission from January
30 yearsSince Democrats last controlled Georgia Power's regulator
~13 pointsHubbard's margin over Fitz Johnson when the AP called the District 3 race on election night
~10 pointsEdwards's margin over Josh Tolbert in the District 5 race
$40Average rise in monthly Georgia Power bills since 2023, per State Affairs

The Associated Press called both races on Tuesday night, with Hubbard leading Johnson by 13 percentage points and Edwards leading Tolbert by 10 at the call; later counts reported by MLQ News put the final margins at 12.8 points and 10.6 points. Commissioners must live in one of the commission's five districts but are elected by voters statewide, and the results remain unofficial until they are certified. The commission regulates Georgia's utilities, including Georgia Power, the Southern Company subsidiary that is the state's largest electricity provider — meaning its five commissioners have the final say over how that power is generated and how much customers pay for it.

Source: The Current GA, Nov. 4, 2026; MLQ News, Nov. 7, 2026

Thirty Years of One-Party Control, Broken in Two Elections

The five-member commission was made up entirely of Republicans from 2006 until the start of this year. The break began in special elections last year, when Hubbard and Alicia Johnson unseated Republican incumbents amid mounting frustration over rising power bills — above all a series of rate increases attached to the construction of two new nuclear reactors at Georgia Power's Vogtle plant, which ran years behind schedule and billions of dollars over budget. Through this year, Hubbard and Johnson cast dissenting votes on commission decisions while stressing that a third Democratic vote would let them actually change outcomes. Edwards ran explicitly on being that vote: "I'm running to join them, to be that third critical vote to change the trajectory of what's going on in our state," she said during an Atlanta Press Club debate this fall, as reported by The Current.

Source: The Current GA, Nov. 4, 2026; Heatmap News, Nov. 4, 2026

The numbers behind the anger are these: Georgia Power has raised monthly bills for its nearly three million customers by an average of about $40 since 2023, according to State Affairs, and the Heatmap-MIT Electricity Price Hub calculates that Georgia rates are up more than 18 percent over the last three years and more than 6 percent over the last two, though by less than 1 percent in the past year. In the run-up to this election, the outgoing commission approved a three-year base-rate freeze proposed by Georgia Power in an attempt to head off public dissatisfaction — a freeze the new majority inherits. "Over the last 12 months, Georgian consumers have made one thing clear: They are tired of rising utility bills and they are hungry to see change. Georgia's sea change moment for energy policy has arrived," Charles Hua, executive director of the utility-focused advocacy group PowerLines, told Heatmap News. Kristin Phillips, an Emory University associate professor specialising in energy policy, told State Affairs: "We need a more active PSC."

Source: State Affairs Georgia, Nov. 5, 2026; Heatmap News, Nov. 4, 2026

The Sealed OpenAI Contract Waiting on Their Desk

The new majority's hardest early test is already on file. In August, Georgia Power's contract to supply a planned 3.2-gigawatt OpenAI data centre in Effingham County passed PSC staff review with the public copy redacted in full as a trade secret; regulators released only a summary after approval, and Hubbard has said the terms would stay secret even after the contract is signed. Georgia Power says data-centre revenue will cover the infrastructure it builds and puts $15 a month of downward pressure on a typical residential bill under the OpenAI deal; to win approval it promised not to recover revenue shortfalls from other customers if OpenAI or another data-centre operator ends its contract early, and agreed to file summaries of future data-centre contracts. Hubbard noted in August that enforcing protections like those takes three commission votes — the three votes Democrats will now hold. OpenAI has separately pledged about one gigawatt of demand response in Georgia under a new grid programme and has promised to pay its campuses' power costs.

Source: MLQ News, Nov. 7, 2026

Data centres were a central argument of the campaign itself. In an October debate with Tolbert, Edwards said of the data centres: "They came into our communities. They didn't pay any taxes. They are using our water, using our electricity, and they're being a public nuisance to the communities that they're coming into." Hubbard, speaking on Heatmap's Shift Key podcast in June, argued for a whole-of-government approach, pointing out that the commission oversees only the power side — where the electricity comes from and what data centres pay for it under their tariffs — while water use and tax incentives sit elsewhere; he put the estimate for Georgia data-centre tax abatements this year at $3.5 billion in uncollected revenue. The races drew unusual national attention for a utility regulator — only ten U.S. states elect their utility commissions at all. Former Vice President Kamala Harris appeared at a virtual fundraiser for the Georgia Democrats, the solar industry spent hundreds of thousands of dollars supporting them, and anonymous donors put millions of dollars behind Tolbert's bid.

Source: Heatmap News, Nov. 4, 2026

What the commission can — and cannot — do to your bill

The PSC sets the rates Georgia Power may charge and approves its long-term energy plans, so the new majority can block or reshape future increases and demand tougher cost protections on data-centre deals. It cannot by itself undo increases already approved, and a three-year base-rate freeze agreed before the election runs into the new term. The next full rate case — the proceeding that decides what customers pay — is due in 2028, the first since 2022.

What Happens Next

Hubbard has said his first priority will be an affordability docket — a series of hearings on high bills — and he set out the majority's programme in a statement on his website: "Winning control of the Georgia Public Service Commission means prioritizing lowering power bills instead of constantly increasing corporate profits, ramping up the deployment of clean energy technologies, and focusing the people in our decision-making as state regulators." Current commissioners also expect Georgia Power to file another update to its long-term energy plan next year, as it did in 2023, driven by data-centre demand; the next full long-term plan is due in 2028, with the rate case to follow. Southern Company chief executive Chris Womack has said the company is confident it can address affordability concerns with the new commissioners; Southern's shares slipped slightly more than 0.5 percent in after-hours trading on election night.

Source: MLQ News, Nov. 7, 2026; The Current GA, Nov. 4, 2026

For Georgia's Punjabi and wider South Asian community — concentrated in the Atlanta suburbs and along the I-75, I-85 and I-20 logistics corridors where trucking, warehousing and small businesses cluster — the commission's decisions land directly on household power bills and on the electricity costs of dhabas, shops, cold storage and workshops. The practical questions for the new majority are the ones this campaign was fought on: whether data-centre growth is billed to the companies driving it or spread across households, and whether the affordability hearings Hubbard has promised produce lower bills before the 2028 rate case. Awaaz Punjab will follow the commission's January start, the affordability docket and the Georgia Power plan filings as they happen.

What is solid

  • Democrats won both PSC seats on the Nov. 3, 2026 ballot — Hubbard in District 3 and Edwards in District 5 — giving the party a 3–2 majority from January, its first control of the commission in 30 years (The Current/GPB; AP calls on election night)
  • The commission was entirely Republican from 2006 until the start of this year; Hubbard and Alicia Johnson won their seats in special elections last year
  • Georgia Power's public contract to supply OpenAI's planned 3.2 GW Effingham County data centre was fully redacted in the public file; only a summary was released after approval (MLQ News)
  • The next Georgia Power rate case is due in 2028, the first since 2022

What is only claimed

  • How much of the data-centre build-out households will ultimately pay for — Georgia Power says data-centre revenue puts $15 a month of downward pressure on a typical bill, while the incoming commissioners argue the costs and tax breaks fall on communities; the sealed OpenAI terms mean the public cannot yet check either claim in full
  • Whether the new majority can actually lower bills before 2028, given the pre-election three-year base-rate freeze and increases already approved