Indian Railways has achieved the main breakthrough of Tunnel-14, a 6.59-km tunnel on the Rishikesh–Karnaprayag rail line in Uttarakhand's Rudraprayag district, with the two excavation drives meeting inside the Himalayan mountain on Friday, 27 November 2026.

Source: Press Information Bureau

The breakthrough connects a 4.7-km stretch driven from Portal-1 at Sumerpur with a 1.79-km stretch excavated from Portal-2 at Marora, the Ministry of Railways said.

Source: IANS

6.59 kmLength of Tunnel-14
4.7 kmDriven from Portal-1, Sumerpur
1.79 kmDriven from Portal-2, Marora

A difficult dig through loose Himalayan soil

At Portal-1, engineers excavated a 110-metre stretch of triple-track tunnel through loose soil beneath inhabited areas, with only 20 to 30 metres of soil and rock above it.

Source: Press Information Bureau

At Portal-2, the slope was secured with 30–35-metre-deep micropiles, 15–20-metre-long rock bolts and consolidation grouting. Those measures allowed the main tunnel drive to begin in March 2024, after ground settlement issues at Marora and matters related to land and home acquisition were resolved.

Source: IANS

Why this tunnel matters

The 125-km Rishikesh–Karnaprayag line will have 12 stations and 16 tunnels, which make up about 83 per cent of the route. Once complete, it is expected to cut the journey from Rishikesh to Karnaprayag from around eight hours by road to about two and a half hours by train, and it will serve as the feeder link for the Char Dham railway project.

Source: NewsNation

Rail Vikas Nigam Limited (RVNL) is executing the project. Work continues on the remaining tunnels and stations; no opening date for the full line has been announced.

The breakthrough was reported by the Press Information Bureau and the IANS news agency, citing the Ministry of Railways.