Indian Railways on Saturday said it has achieved a major breakthrough in the Sivok–Rangpo New Line Railway Project in Sikkim, with excavation work completed in Tunnel No. 10, the longest tunnel on the route.

Source: IANS

The 5.3-km tunnel is the longest of the 14 tunnels on the line. With the two excavation fronts now joined, excavation is complete in all 14 tunnels, bringing Sikkim a step closer to its first railway connectivity, an official statement said.

Earlier: Sikkim's first rail link targeted by June 2028

Awaaz Punjab reported on November 18 that the Sivok–Rangpo line is targeted to give Sikkim its first railway by June 2028. Today's breakthrough is the latest construction milestone on that project. Read the earlier story

5.3 kmLength of Tunnel No. 10, the longest tunnel on the route
14Tunnels on the line — excavation now complete in all of them
45 kmTotal length of the Sivok–Rangpo broad-gauge line
23Bridges on the project

The tunnel was excavated from both ends and through two access tunnels. The remaining work — tunnel lining, track laying and installation of essential railway safety systems — will now progress, the statement said.

The 45-km broad-gauge line passes through Darjeeling and Kalimpong districts in West Bengal and Pakyong district in Sikkim. About 86 per cent of the route runs through tunnels, and the project also includes 23 bridges.

The line will serve the stations of Sivok, Riyang, Melli and Rangpo, along with an underground halt at Teesta Bazaar. At Sivok it will connect with the existing New Jalpaiguri–Alipurduar route, linking Sikkim to the national railway network.

Once operational, the line will give residents and tourists a safer, faster and more reliable alternative to National Highway 10, besides helping essential goods move, giving local businesses better access to markets and boosting tourism, Railways said.

Source: IANS