Kathmandu — Nepal's Cabinet has authorised the Finance Ministry to formally seek a one-year extension of the $747-million Millennium Challenge Corporation (MCC) compact, the US-funded programme building a high-voltage transmission line and upgrading a stretch of the East-West Highway.

Source: Tezzbuzz

The compact entered into force on August 30, 2023, and its five-year implementation window runs out in August 2028. The extension would push the completion deadline to August 2029. The Cabinet's decision carries one condition: the cost of the project must not rise during the extra year.

Source: Patrukar

The programme is worth $747 million in total — $550 million from the United States and $197 million from the Government of Nepal. Its centrepiece is a 315-km, 400 kV electricity transmission line, along with upgrades to a section of the Mahendra Highway.

Source: Tezzbuzz

The extension is not final yet. Nepal will now send a formal request to the MCC board, which must approve the revised timeline before the new deadline takes effect. A decision is expected at the board meeting in December.

Source: Tezzbuzz

The request has been in the works for months. Millennium Challenge Account Nepal, the agency implementing the compact, asked the Finance Ministry in mid-May 2026 to approach MCC for the extra year, saying managers needed more time to finish the work.

Source: Asia Daily

Finance Minister Dr Swarnim Wagle discussed the extension with MCC Acting Vice President Jason Small during his visit to the United States, and both sides agreed an additional year was needed to complete the projects.

Source: Tezzbuzz

The compact was signed on September 14, 2017. The United States later added $50 million to its grant, and Nepal added $67 million in May 2023 after the cost of the transmission project rose above its budget.

Source: Tezzbuzz

Work on the compact was disrupted after the US government began a review of foreign aid programmes in January 2025. In the last week of July 2025, Washington recommended the MCC project in Nepal continue. The board's December decision will now determine whether the projects get the extra year they need.