The estimated cost of the Mumbai–Ahmedabad bullet train project has nearly doubled to ₹2,02,797 crore (about ₹2.03 lakh crore), the National High Speed Rail Corporation Ltd (NHSRCL) has disclosed in a reply to a Right to Information (RTI) application, with no firm date yet for completing the full 508-km corridor.

Source: Metro Rail Today

The revised figure is almost double the original estimate of ₹1,08,000 crore. NHSRCL said it had already spent ₹92,761 crore on the project as of March 2026.

The corridor, launched in 2017, has already run years past its original completion target. Asked about a revised timeline, NHSRCL said the completion date “can be ascertained after award of all contract packages” — meaning the full line still has no fixed finish date.

First section due in December 2027

The first section, between Surat and Vapi in Gujarat, is expected to open in December 2027, according to reports. The 50-km Surat–Bilimora stretch was energised on November 20, the first section of the corridor to receive power.

The project will now begin operations with indigenously built trainsets from BEML Ltd instead of Japanese Shinkansen trains as originally planned. The first BEML trainset is scheduled for dispatch in February 2027.

The 508-km corridor, with 12 stations, connects Mumbai and Ahmedabad through Maharashtra, Gujarat and Dadra and Nagar Haveli. Delays have been blamed on land acquisition and compensation issues, among other factors.

₹2,02,797 croreRevised project cost
₹1,08,000 croreOriginal estimate
₹92,761 croreSpent till March 2026
508 kmCorridor length

A proposal on the revised cost estimate has been placed before the Union Cabinet, reports said, with no official briefing following the meeting.