Kaiga Generating Station Unit-1 in Karnataka was synchronised back to the electricity grid at 1:58 pm on Sunday, November 29, the Nuclear Power Corporation of India Ltd (NPCIL) announced, completing the reactor's return to service after a 600-day refurbishment outage.

Source: NPCIL

The 200 MWe pressurised heavy water reactor had attained criticality — the start of the controlled fission process — early in the morning of November 22, a week before the grid connection. NPCIL said the 600-day turnaround set a new fleet-wide benchmark, as the first of its reactors to reach criticality so quickly after such a major outage.

Source: World Nuclear News

The unit was shut down on April 1, 2025, to replace its coolant channels and feeders. The work involved removing the fuel, draining the heavy water that cools and moderates the reactor, replacing the coolant channels, inspecting the reactor core, reloading the fuel, and a series of leak, pressure and conditioning tests before the approach to criticality.

Source: World Nuclear News

Kaiga-1 first reached criticality on September 26, 2000, and had supplied 37,670 million units of electricity before it was shut down for the life-extension refurbishment in April 2025.

Source: Coastal Talk News

The restart comes as India's nuclear regulator, the Atomic Energy Regulatory Board, also cleared Rajasthan Atomic Power Project Unit-8 — a 700 MWe reactor — for its first approach to criticality on November 19, after safety reviews and inspections.

Source: World Nuclear News

200 MWeKaiga Unit-1 capacity
600 daysRefurbishment outage
22 Nov 2026Criticality attained
29 Nov 2026Synchronised to grid
Earlier story

Kaiga Unit-1 attained criticality on November 22 after the record 600-day refurbishment. Read the earlier story