State-run Oil and Natural Gas Corporation (ONGC) has taken over operations and control of the disputed Cambay offshore block from Vedanta Oil & Gas Ltd, according to regulatory filings by the two companies reported on November 15. Vedanta has recognised an impairment charge of about ₹379 crore against assets and receivables linked to the block.

Source: The Hindu BusinessLine

The takeover of the CB-OS-02 block took effect on July 22, 2026, after the Delhi High Court's single-judge bench dismissed Vedanta's challenge to the government's decision not to extend the production-sharing contract, ONGC said in its quarterly filing. ONGC subsequently took custody of the block and applied for a petroleum lease on July 28.

Source: TradingView News

₹379 croreVedanta impairment charge, Q1 FY27
50%ONGC participating interest
40%Vedanta participating interest
10%Invenire Petrodyne interest

A contract that expired in 2023

The production-sharing contract for the Cambay block expired on June 29, 2023. Vedanta and its joint-venture partners had applied for an extension on June 28, 2021, under the government's 2017 extension policy. The government, through a letter dated September 19, 2025, declined to extend the contract and directed the operator to hand the block over to ONGC. Vedanta challenged that decision in the Delhi High Court on September 22, 2025, and an interim order had directed that the status quo be maintained until the petition was dismissed on July 22, 2026.

Vedanta said it stopped recognising revenue and related expenses from the Cambay block from the date of the July 22 order, citing the absence of a valid production-sharing contract and uncertainty over recovering its assets and receivables. ONGC said it accounted for its interest in the block as an unincorporated joint venture up to July 21, 2026, and has operated it under the terms of the nomination regime since taking over. Decommissioning liabilities will be met from the block's site restoration fund, while other future liabilities from petroleum operations will be borne by ONGC for as long as it operates the block, the company said.

Appeal heard, judgment reserved

The legal dispute is not over. Vedanta has appealed the single-judge order before a division bench of the Delhi High Court; hearings concluded on October 1 and the judgment has been reserved, according to the filings. Both companies said the ultimate outcome of the litigation and any consequential financial impact cannot be determined at present.

Why it matters

The case is a live test of India's production-sharing contract regime: an operator has lost an offshore block after the government refused an extension, and the final word now rests with a division bench of the Delhi High Court.