Texas environmental regulators have resumed reviewing permits for data-center projects, ending a pause on approvals that Governor Greg Abbott ordered this fall — even though the grid audit behind the pause is not finished yet.
Source: Texas Tribune / KTTZ
The Texas Commission on Environmental Quality (TCEQ) received notice on Friday, November 13, from the governor's office that the Electric Reliability Council of Texas (ERCOT) had completed gathering information on potential community impacts from data centers — one part of the audit Abbott ordered. Days later, on November 16, the agency issued an air permit for a data center and gas-fired power plant.
Source: Gibson Dunn
"The agency has resumed its normal permit review process and will evaluate applications under all applicable state and federal laws and regulations," TCEQ spokesperson Laura Lopez said in a written statement.
Source: Texas Tribune / KTTZ
What the pause was
In August, Abbott directed the Public Utility Commission of Texas and ERCOT to audit every data center advancing through the grid-interconnection process, and directed the Texas Water Development Board to enforce water-use reporting. Then, in a September 21 letter, he told TCEQ to issue no permits sought by data-center projects until ERCOT completed its audit. The directive set no fixed end date.
Source: Gibson Dunn
The audit covers far more than paperwork: grid officials are examining tax incentives, power use, water use and potential neighbourhood impacts from the wave of power-hungry facilities seeking to connect to the Texas grid.
Source: Texas Tribune / KTTZ
Shortly after permit reviews restarted, TCEQ authorised emissions associated with SpaceX's proposed use of 43 generators at its planned data-center site near Brownsville, according to a November 16 letter from the agency. Environmental groups had complained days earlier that SpaceX had begun building without a permit.
Source: Insurance Journal
Why the timing matters
The restart comes in the middle of a political handover. In a stunning upset on November 3, Abbott lost his re-election bid to Democrat Gina Hinojosa, who campaigned on keeping data-center approvals paused until legislators pass new state laws. She takes office on January 19, 2027.
Source: Texas Tribune / KTTZ
The restart has drawn criticism. Public Citizen criticised the decision to resume permitting before ERCOT's findings are public and called on TCEQ commissioners to resign, arguing the public deserves to see the full community-impact picture first.
Source: Texas Tribune / KTTZ
What it means for Texans
Data centers are among the hungriest users of electricity and water in the state, and Texas has become one of the top destinations for them. Supporters point to construction jobs, tax revenue and the tech industry's growth; nearby residents and local officials worry about strain on the grid, rising electricity costs and water supplies — the exact concerns ERCOT's audit was ordered to measure.
Source: Insurance Journal
ERCOT gave regulators an update on November 5, reporting responses from 93 percent of the 465 projects in its review — enough, it said, for a statistically meaningful analysis of the final report. But the full findings are still to come, and the agency has said it is still working to complete its audit.
Source: Texas Tribune / KTTZ
ERCOT plans to report its full findings to the Public Utility Commission on December 10 and discuss them at the commission's open meeting on December 17 — the earliest date the audit can be treated as complete. Governor-elect Hinojosa takes office on January 19, when a new legislature can revisit the rules governing data-center approvals.