Bhagalpur: The Bihar Cabinet on Wednesday (November 18) approved the selection of Adani Energy Solutions Limited to develop the power transmission network for the proposed 2,400 MW Pirpainti thermal power plant in Bhagalpur district, according to an official statement.

Source: The Hindu BusinessLine

The transmission system will carry the electricity generated at the plant to the power grid for supply to consumers. The company was selected through an online bidding process, the statement said.

Rs 493.76 crore a year for 35 years

Adani Energy Solutions will receive Rs 493.76 crore annually for 35 years for developing and operating the project. The amount will be paid jointly by the North Bihar Power Distribution Company and the South Bihar Power Distribution Company, subject to approval by the Bihar Electricity Regulatory Commission.

At the end of the 35-year period, the entire transmission infrastructure will be handed over to Bihar State Power Transmission Company Limited free of cost, the statement said.

The decision was taken at a cabinet meeting chaired by Chief Minister Samrat Choudhary. The state government said the project is expected to strengthen Bihar's power-supply system and help meet rising electricity demand, and described the transmission network as a critical enabling component that will connect the Pirpainti plant with the wider grid.

The official statement did not provide details of the transmission network's route, its construction schedule or the plant's commissioning timeline. The annual payments also still require the state electricity regulator's approval.