Federal auditors warned on Thursday that U.S. Immigration and Customs Enforcement has spent billions of dollars expanding immigration detention without determining whether its new initiatives are cost-effective — or even keeping its spending plan up to date.
Source: ABC News
The Government Accountability Office, Congress's nonpartisan watchdog, released its report, "ICE Should Determine Cost Effectiveness of New Initiatives Before Continuing," on November 19. It examined how ICE has managed the $45 billion in detention funding Congress provided in July 2025 through the One Big Beautiful Bill Act, money available through fiscal year 2029.
Source: Sen. Dick Durbin
Eleven warehouses bought, seven now for sale
From January to March 2026, ICE bought 11 warehouses to convert into immigration detention centres for about $1.07 billion, the report says. The agency then scaled the initiative back significantly and now plans to sell seven of them.
For nine of the 11 warehouses, ICE paid at least 50 percent more than the state or local government's assessed taxable value, auditors found. The facilities ranged in cost from $35 million to $145 million each.
In July and August 2026, ICE also bought four existing detention facilities for about $2.2 billion in total, according to the report. But the scope, time frames and estimated costs of further acquisitions remain undetermined, GAO said.
Money spent on facilities never used
The report also documented nearly $3 million spent erecting tents at Guantanamo Bay that were never used, and $20 million to maintain purchased warehouses that are now being sold without having housed a single detainee, according to the GAO's findings.
Meanwhile the population in ICE detention has grown sharply — from about 39,000 people in January 2025 to about 67,000 as of July 30, 2026 — even as the agency's planning has lagged behind its spending, the report says.
What the auditors recommended
GAO recommended that ICE update its spending plan for detention funding in line with internal guidance, and develop life-cycle cost estimates — the full cost of owning and running a facility over its lifetime — in coordination with the Department of Homeland Security, before making new detention investments. The Department of Homeland Security agreed with both recommendations, according to the report.
The agency has told GAO it will develop a comprehensive strategic plan to guide its detention expansion, but not until August 31, 2027 — a date the auditors warned may be too late to prevent further waste.
Why this matters
The report was released by Senator Dick Durbin of Illinois, the Senate's Democratic Whip and ranking member of the Senate Judiciary Committee, whose office said the findings show wasteful spending under the Trump administration's detention expansion. GAO investigated at the request of congressional Democrats.
For immigrant communities — including the large Punjabi and South Asian communities across the United States — the scale of the detention build-out matters directly: more beds, more facilities and faster arrests have meant more families separated by detention, more bond hearings in federal courts, and more people held far from home while their cases proceed.
What happens next
Congress is expected to press DHS and ICE on the findings in oversight hearings, and the spending plan update GAO demanded will be the first test of whether the agency changes course. The report does not announce any new facility purchase; it is an audit of decisions already made — and a warning about the ones still to come.
ICE received $45 billion to expand detention. GAO found it bought warehouses above assessed value, abandoned most of the plan, and still has no full cost picture — and DHS has agreed to fix it.