Railway Minister Ashwini Vaishnaw said on Friday that India's first high-speed rail service will begin in the last quarter of 2027, with the first section to open between Surat and Vapi in Gujarat. The full 508-km Mumbai–Ahmedabad corridor will follow in phases, he said.
Source: Deccan Herald
Vaishnaw shared the timeline in a post on Substack, setting out the pace of construction on the Mumbai–Ahmedabad High-Speed Rail corridor and the manufacturing of India's first indigenous bullet train.
Construction so far
As of September, 456 km of pier work and 371 km of viaduct construction have been completed, the minister said. Six lakh noise barriers have been installed along a 299-km stretch, and 9,300 overhead electrification masts have been put up across a 206-km viaduct.
In Maharashtra, the corridor runs through a 21-km tunnel, including a 7-km stretch under the sea beneath Thane Creek — India's first undersea rail tunnel. Two tunnel boring machines were launched in July 2026 from Vikhroli and Sawli, among the largest ever used in India.
The indigenous B28 trainset
The B28 trainset is being manufactured jointly by the Integral Coach Factory (ICF) and Bharat Earth Movers Limited (BEML). Designed for a test speed of 280 kmph, its first body frame is complete and undergoing structural testing, with track trials expected by mid-2027. A faster B35, designed for 350 kmph, is the next step, Vaishnaw said.
Source: Indian Economic Observer
The eight-coach trainset will be about 202 metres long and carry 557 passengers. Once the full corridor opens, the Mumbai–Ahmedabad journey will take 1 hour 58 minutes, against 8 to 9 hours by road today. Vaishnaw said fares will be kept affordable so the middle class can use the service.
Work is in progress at all three rolling stock depots — at Sabarmati, Surat and Thane. The project, first announced in 2017, was delayed by land acquisition and state permissions in Maharashtra and by the Covid-19 pandemic, the minister said.
Track trials of the B28 are expected by mid-2027. The Surat–Vapi section opens first in the last quarter of 2027, and the remaining stretches to Mumbai will follow in phases.
Earlier this week, the first 50-km Surat–Bilimora stretch of the corridor was powered up, another milestone on the same route. Read the earlier story