New Jersey told a federal judge on Friday that it will ask the court to enforce its May order halting work on the Roxbury warehouse, arguing that the $31.8 million renovation contract ICE signed on November 5 violates that order. Judge Jamel K. Semper signed off on an expedited briefing schedule the same day.

Source: CourtListener — Document 58, filed Nov. 20, 2026

Earlier: the contract documents

New Jersey first pressed the government for the contract in a court filing on November 16, after learning of the $31.8 million deal. Days later, the government produced 178 pages of contract documents. Read the earlier report

What the state filed on Friday

In a letter dated November 19 and filed on November 20 as Document 58, Shankar Duraiswamy, counsel for the State of New Jersey, told Judge Semper that the plaintiffs intend to file a motion to enforce the court's May 12, 2026 order. The state asked for an expedited briefing schedule: its motion is due November 23, the government's opposition is due December 2, and the state's reply is due December 7. The government's lawyers told the court they do not consent to that schedule. Judge Semper signed the letter "So Ordered" on November 20.

Source: CourtListener — Document 58

The documents the government produced earlier this week — filed as exhibits 56-1 to 56-3 — show that ICE entered into a contract on November 5, 2026 that commits over $31 million in taxpayer funds to renovating the Roxbury warehouse into a detention center. To date, the government has not completed the required environmental assessment. The state writes that the contract commits tens of millions of dollars to renovations "in direct contravention" of the May 12 order.

Source: Project Salt Box

$31.8MContract signed Nov. 5 with SK2 LLC
470,000 sq ftWarehouse at 1879 Route 46, Roxbury
Nov. 23State's motion to enforce due
500–1,500Detainees the planned facility would hold

What the May order requires

The May 12 order bars the Department of Homeland Security and ICE — subject to certain limited exceptions — from undertaking activities at the Roxbury warehouse site "for purposes of converting it into a detention center" until two things happen: first, the agency issues an initial environmental assessment, and second, New Jersey and Roxbury get a chance to challenge the assessment's findings in a renewed preliminary injunction motion. In the meantime the order permits only narrow work: temporary fencing that does not disturb the ground, security cameras and lighting, an alarm system, new locks, and routine maintenance of the building's heating, plumbing, electrical and fire systems.

The state's argument is that an environmental assessment is supposed to take a "hard look" at a project before the government commits resources to it. The purpose of the May 12 order, the state writes, was to freeze the status quo so that assessment could be genuine. Attorney General Jennifer Davenport warned in the November 16 status report that if the government has already committed resources to converting the facility, "then any forthcoming [environmental assessment] will be mere window dressing for a decision that has already been made."

The government's shifting account

The federal government's account of its plans has changed several times. It bought the 470,000-square-foot warehouse at 1879 Route 46 in February for $129.3 million. New Jersey and Roxbury Township sued in March to stop the conversion. In May, the court order froze the work. In June, government lawyers told the court the department no longer planned to convert the warehouse and intended to sell it. In July, they said the agency would "consider the retrofitting" of the building, then said it had no timeline for deciding. In August, ICE sought bids from companies to do the work; SK2 LLC, a Tennessee-based firm, submitted its offer on September 4. On September 15, the government told the judge it had "no timeline" for deciding what to do with the warehouse. On September 4 and September 8, ICE acknowledged it detained 14 people at the site for processing. On November 5, ICE signed the contract with SK2. Project Salt Box first reported the $31.8 million award on November 6; when the state's lawyers asked about it that day, the government's lawyers "could not confirm" whether the report was correct — and then told the state for the first time that the department had decided to move ahead. On Monday, November 16, the government told the court that ICE "currently intends to retain the Roxbury facility and renovate it to some level of detention capacity." On Tuesday, November 17, it filed 178 pages of contract documents, including the signed order with SK2 and a 158-page performance work statement.

Source: Project Salt Box

The Justice Department's position, set out by Principal Deputy Assistant Attorney General Adam R.F. Gustafson, is that the contract covers maintenance of the property, design of ICE's preferred plan for converting the warehouse, and conducting the environmental review — and that ICE will renovate the facility "in accordance with" the judges' May order. The state disputes that reading, pointing to contract terms that would let ICE approve construction of offices at the site while the environmental review is still underway.

A tense hearing in Congress

At a House Homeland Security Committee hearing on Wednesday, November 18, Representative Analilia Mejía pressed Homeland Security Secretary Markwayne Mullin over the same contract. Asked whether the court-required environmental review had been completed, Mullin replied: "I don't know if it's been completed or not." He told the committee the project was still being put out for bid — even though the contract had been signed on November 5. Mejía also raised ICE's admission that 14 people were detained at the Roxbury site on September 4 and September 8 for processing; Mullin said he was not familiar with that.

What the state is asking for

New Jersey wants the court to enforce the May 12 order and stop the government from spending on conversion work before the environmental assessment is done. Its motion is due November 23; the government's response is due December 2; the state's reply is due December 7.

Why it matters for New Jersey families

Roxbury Township Council — dominated by Republicans — voted unanimously to oppose the detention facility, and residents have raised concerns about water, sewage, public safety and the environment around the site. New Jersey is home to a large immigrant community, including many Punjabi families, and this case will decide whether federal agencies must finish an environmental review before building detention capacity in a town that never agreed to host it. The Roxbury fight runs alongside the state's separate lawsuit filed November 17 against Homeland Security over its refusal to answer subpoenas about conditions at Delaney Hall, the privately run ICE detention centre in Newark.

What happens next

New Jersey's motion to enforce is due November 23, the government's opposition on December 2, and the state's reply on December 7. The judge will then decide whether ICE violated the May 12 order. The environmental assessment itself is still pending. If the court finds a violation, it could halt the work the contract has already set in motion.

At Wednesday's hearing, Representative Analilia Mejía pressed DHS Secretary Markwayne Mullin over the same contract — and he could not say whether the environmental review had been completed. Read about the hearing

A note on the record: the figures in this report come from court filings and government contract documents. The state's claim that the contract violates the May order is an allegation the court has not yet ruled on; the government disputes it.