The Supreme Court has granted an interim stay on the 130-acre 'One Goa' township project at Karapur village in North Goa, halting the technical clearances and construction licences issued for the first four buildings of the House of Abhinandan Lodha (HoABL) project.

Source: Hindustan Times

The order, passed on 27 November, also stays all construction activity at the project site. The stay was granted ex parte, and the matter is scheduled to be heard again in January.

Source: Mirror Now

What the court stayed

The court stayed the operation of technical clearance orders dated 2 September 2025, 31 October 2025 and 1 June 2026, and suspended the construction licences issued on 27 September 2025 and 4 December 2025 for the first four buildings.

Source: Mirror Now

The petition was filed by Pravinsingh Shedgaonkar, who alleged that the Town and Country Planning Department granted the clearances despite a Supreme Court status-quo order of July 2025 on approvals under Section 17(2) of the Goa Town and Country Planning Act. Goa Foundation director Claude Alvares announced the order at a press conference after it was passed.

Source: Goa Foundation

The petition challenges a Bombay High Court order that had disposed of Shedgaonkar's earlier petition. He was represented in the Supreme Court by Senior Counsel Shoeb Alam, along with advocates Sivagnanam Karthikeyan and Ira Mahajan.

Source: Goa Foundation

The petitioners have also filed a contempt petition against Chief Town Planner Vertika Dagur and Bicholim Town Planner Shiv Prasad Murari, alleging that the officials granted the clearances in violation of the court's earlier status-quo order.

Source: Goa Foundation

The developer has maintained that all approvals for the project are in place and that it complies with RERA and Town and Country Planning laws. The interim order is a pause on specific approvals, not a final verdict on the project.

Source: Mirror Now

What happens next

The stay covers the approvals and licences for the first four buildings only. No construction can proceed on those buildings until the Supreme Court hears the matter in January.

What is solid

  • The Supreme Court passed an interim stay on 27 November 2026.
  • The stay covers technical clearances and construction licences for the first four buildings of the One Goa project at Karapur.
  • All construction at the site is stayed until the next hearing in January.

What is only claimed

  • Whether the Town and Country Planning clearances violated the Supreme Court's July 2025 status-quo order — the petitioners' allegation, which the court is yet to decide.
  • Whether the developer's approvals are valid — the developer says all approvals are in place and lawful.