Construction on the nearly $500 million upgrade to Folsom Dam — the flood-protection project that guards more than 500,000 people in California's Sacramento region — could grind to a halt in January 2027 unless new federal funding arrives, the U.S. Army Corps of Engineers has warned.

Source: CBS News Sacramento

~$500 millionTotal cost of the Folsom Dam upgrade
~$300 millionAlready spent on the project
1 of 8Spillway gates modified so far
500,000+People in the Sacramento region the project protects

What the project is supposed to do

Work on the project began in 2019. The plan is to raise the dam's dikes and fit new top bulkheads — heavy steel seals — on all eight of the dam's metal spillway gates, adding three feet of holding capacity so Folsom Lake can store more water during major winter storms. The 340-foot main dam itself is being raised by 3.5 feet, along with the left and right wing dams, the Mormon Island Auxiliary Dam and the eight dikes around Folsom Lake.

Source: U.S. Army Corps of Engineers

So far, only one of the eight gates has been modified. The bulkheads for the remaining seven gates have already been manufactured and are sitting at the site, and one gate is currently out of service because of the construction. The Corps awarded a $114.4 million construction contract for the dam modifications in April 2023 to Folsom Dam Constructors, a joint venture of Shimmick Construction and California Engineering Contractors. Dike 8, on the southeastern side of Folsom Lake, was the first to be raised, in 2020, and work on Dike 6 began in December 2024.

Why the money ran out

The Corps needed additional funding by the end of August but did not receive it, and the project is now running on what remains of money already appropriated. The squeeze is part of a wider pullback: according to the Governor's Office, the Trump administration's fiscal year 2025 Army Corps work plan gave no construction money to four California flood-control projects that had been set to receive a combined $126.4 million, and its fiscal year 2026 budget asked for $1.56 billion for Corps construction — 53 percent less than Congress enacted for fiscal year 2024. The administration also cancelled the Federal Emergency Management Agency's Building Resilient Infrastructure and Communities programme, and California and 19 other states sued; courts have ordered the programme's funds restored.

Source: Governor's Office, via United States Tribune

The Sacramento Area Flood Control Agency, the regional body that shares the cost of the work with the state and the Corps, is lobbying federal officials and lawmakers for more money. State flood officials raised concerns about the funding gap at a hearing last month. Representative Doris Matsui, whose district includes Sacramento, has said more than $4 billion in federal funding has been secured for the region's flood protection, including $1.1 billion for Folsom Dam and its auxiliary spillway and $485 million for the dam raise.

What it means for Sacramento

Folsom Dam, about 25 miles northeast of Sacramento on the American River, is the cornerstone of the region's flood defences. The Sacramento region is also home to a large Punjabi community — nearby Yuba City has one of the largest Punjabi populations in the United States — and many Punjabi families and businesses live and work in the area the project protects. Flood officials say the work stoppage is not expected to affect flood-control operations this winter, but every winter the unfinished gates go without the extra three feet of capacity is a winter with less margin against a big storm.

The Oroville warning

The stalled work echoes the scrutiny of California's ageing dams that followed the 2017 Oroville Dam spillway crisis, when damage to the tallest dam in the United States forced the evacuation of nearly 200,000 people downstream. Folsom Dam is about 70 years old. Its auxiliary spillway was completed in 2017, and a later survey by the Corps and the U.S. Bureau of Reclamation found corroding steel rods in the spillway gates — a flaw that could have stopped the gates operating.

What happens next

Everything now turns on whether federal appropriations arrive before January. If the money comes, work can resume on the seven remaining gates, with the Corps expecting construction across the dam system to be complete in 2028. If it does not, the gates stay as they are — one modified, seven waiting, their bulkheads already built and sitting at the site — and the delay is likely to add millions of dollars to the final cost. Residents can follow updates from the Sacramento Area Flood Control Agency and the Corps' Sacramento District.

Reporting: CBS News Sacramento (CBS13); project details from the U.S. Army Corps of Engineers, Sacramento District, and Engineering News-Record; funding context from the Governor's Office.