New York City has ordered the controlled demolition of the building next door to the Brooklyn apartment block that collapsed last week, after engineers found the damaged structure too unstable to save. The Department of Buildings announced the decision on Wednesday, November 18 — exactly a week after the three-storey building at 1321 Flatbush Avenue in Flatbush caved into a construction excavation, killing eight people and injuring 18 others.

Source: Engineering News-Record

"Given the dangerous condition of the building and the imperative to make sure no one else gets hurt, ordering for the controlled safe demolition of the building is the only available option," Buildings Commissioner Ahmed Tigani said in a statement. Forensic engineers determined that workers could not safely enter 1323 Flatbush Avenue to carry out the heavy-duty shoring needed to stabilise it, and the agency issued an Immediate Emergency Declaration for its demolition, with a fenced collapse zone set up around the building.

Source: Engineering News-Record

8people killed in the November 11 collapse
18people injured
24jobsites inspected in the citywide sweep
5sites hit with stop-work orders

What happened on November 11

Just after 4 p.m. on Wednesday, November 11, the three-storey mixed-use building at 1321 Flatbush Avenue collapsed into the open excavation at the neighbouring construction lot at 2625 Bedford Avenue, where a developer planned a new building. Six people died at the scene and two more died in hospital. More than 250 firefighters worked through the night, and the Fire Department of New York concluded its search-and-rescue operation on the afternoon of November 12, saying no further victims remained at the site.

The New York Police Department identified the six adults killed as Gabriel Siguencia, 22; Barry Mamadou, 23; Jose Luis Caguana Cosquillo, 26; Edgar Sapon, 26; Ndiaye Mamdou, 31; and Juan Daniel Salvada Guzman, 31. Two children, aged 9 and 10, were also killed. Two of the dead were construction workers, and the victims also included a food-delivery worker and an Amazon worker, according to local reporting on the victims.

The building next door

The building ordered demolished, 1323 Flatbush Avenue, was heavily damaged when its neighbour fell and has continued to deteriorate while its interior has been exposed to the weather, the Buildings Department said. Before demolition can begin, contractors must first install shoring inside 1325 Flatbush Avenue. Full vacate orders remain in effect at 1325 and 1327 Flatbush Avenue. The department has also ordered parts of the excavation at 2625 Bedford Avenue backfilled and paused debris removal while it prepares an independent forensic engineering review. Its full stop-work order at the construction lot remains in force.

A citywide sweep of linked sites

The collapse has triggered a wider inspection blitz. The Buildings Department has inspected at least 24 jobsites in four boroughs tied to the two engineers on the Flatbush project — Jieming Wang of LMW Engineering and MD Ariful Islam — and issued full or partial stop-work orders at at least five of them, Gothamist reported. The sweeps are part of a broader review of roughly 160 projects involving six firms connected to the Flatbush job. Most violations found so far involve scaffolding, guardrails and other jobsite safety issues; only one of the stop-work orders involved excavation, the central concern in the Flatbush investigation.

Source: The Real Deal

Lawsuit says cracks were reported in October

A tenant of the collapsed building has sued his landlord and the developers next door, alleging that warnings about cracks went ignored. Dengane Omari Jack, a Brooklyn musician who lived at 1321 Flatbush Avenue, filed the complaint in Brooklyn Supreme Court late on Monday, November 16. The suit says he reported cracks near the entrance of the property to landlord Olufemi Falade, who owns the building through Isolag Realty Corp, weeks before the collapse. It also names the companies tied to developers Robert Fischman and Judy Swimer, who own the construction lot. Building records reviewed by Gothamist show a pre-construction survey had already judged the side wall of 1321 Flatbush Avenue, the wall facing the excavation, to be in poor shape. Excavation plans called for steel bracing beams, known as rakers, along the whole perimeter of the lot — except the stretch where the building collapsed.

Source: Courier NY / Gothamist

A site with a troubled history

The collapsed building, built in 1930, had 98 open housing-code violations — including unsafe electrical wiring — when it fell. The city issued a stop-work order at the construction site in March 2026 over missing safety measures, and fined the demolition contractor $10,000 for continuing work anyway. The lot was approved for a three-storey building; plans for a nine-storey building had not been approved.

What happens next

Demolition of 1323 Flatbush Avenue will begin only after shoring is installed at 1325 Flatbush Avenue, a job the department said should start this week. The cause of the collapse remains under investigation, and the Buildings Department has not yet determined what brought the building down. Mayor Zohran Mamdani has pledged a full investigation into the collapse and the oversight of the site.

The dead include construction and delivery workers — jobs many newcomers to New York depend on — and the investigation, together with the sweep of linked construction sites, will test whether the city's building-safety system catches dangerous sites before they fail again.

Awaaz Punjab reported the collapse itself and the end of the search-and-rescue operation last week. Read the earlier report